Description of Project
Work under this Contract will include geotechnical consulting services
and materials testing services related to subgrade observations, compaction testing
of soils, observation and compaction testing of hot mix asphalt production, cast-in-place
concrete inspection, and concrete compression test cylinders.
Duration of Work
Completion time is limited to 90 calendar days.
Engineering Estimates
$15,000
Bid and other Dates
Sealed bids received until: June 17, 2010, at 3:00 p.m.