Consolidated Borough of Quil Ceda Village

MBR Treatment Facility Upgrade

Tulalip Tribes Bid Solicitation Number 2017-004

Project Manager for the Project

The Tulalip Tribes of Washington

8802 27th Avenue NE
Tulalip, WA 98271-9694
Attn: Mr. Lukas Reyes
Telephone: 360-716-5022

lreyes@tulaliptribes-nsn.gov

Description of Project

This Tulalip Tribes project provides for the improvement of their Membrane Bioreactor (MBR) Wastewater Treatment Plant (WWTP). The construction of this project includes:

  1. Supply and installation of a headworks drum screen.
  2. Supply and installation of two blowers, sanitary sewer piping, and supports.
  3. Supply and installation of Kubota submerged membrane units (SMUs) in MBR tanks. Supply includes all piping up to and including air and permeate 2-inch isolation valves.
  4. Stainless steel and ductile iron pipe supply and installation.
  5. Supply and installation of electrical motor control center (MCC), duct banks, conduit, and fiber optic cable.

All incidental and related work to complete.

Bid and Other Dates

  • Mandatory Pre-Bid Questions: All pre-bid questions and clarifications should be made in writing to the Contruction Manager no later than five (5) working days prior to bid opening - see Notice to Bidders.
  • Bid Due Date: May 7, 2018 at 2:00 PM